How can Tom and Sally schedule the annual report project?
How can Tom and Sally schedule the annual report project? (IntroductionToBusiness OP 8D04gAa · 2026-10-07-36573 · Preparing for Tomorrow's Workplace Skills) —…
Ideas in this flowchart
- Plan the annual report project for L-Z Marketing's aerospace client
- The agency must create the client's annual report
- Tom Lawrence and Sally Zickle co-own L-Z Marketing, which has won the client
- Tom's responsibilities
- Develop the preliminary report design: 1 week
- Set the type: 2 weeks
- Print the report: 3 weeks
- Sally's responsibilities
- Meet with the client to review financial information: 2 days
- Write the report copy: 3 weeks
- Proofread the report: 3 days
- Project scheduling constraints
- Sally must review the client's financial information before writing the copy
- Tom's design work and Sally's initial work can proceed in parallel
- Tom cannot set the type until the design and Sally's report copy are finished
- Sally must proofread the report before it goes to the printer
- Printing follows the completion of proofreading
- Use a critical path diagram because the project depends on task relationships and completion constraints
- Critical path duration: 2 days + 3 weeks + 2 weeks + 3 days + 3 weeks
- With no unforeseen delays, the project will take 45 working days, or 9 weeks